XL Catlin FitoutSydney / July 2017
1,500m2 office fitout completed in 10 weeks over 3 stages in a live environment and included open plan workspace, new meeting/boardrooms, breakout areas and Reception
Procurement of items for this project was a challenge; particularly in stage 1 where the new break out area was completed in 3 weeks. Loan furniture was provided for the space as an interim solution until the specified furniture was delivered.